Why this control matters
Machinery hire decisions become difficult to compare when requirements remain implied. This protocol creates a compact evidence trail: what the project needs, what the supplier has offered, what remains to be confirmed and who owns the next decision.
Control sequence
- 01
Define output and working envelope
Describe the quantity, material, required result and working position. Attach a plan with dimensions. Ask suppliers to state the proposed machine class and how it meets those inputs; keep productivity estimates identified as assumptions until the site has been assessed.
- 02
Separate base hire from mobilisation
Ask for delivery and collection as separate line items, including origin, waiting and loading assumptions. Keep fixed mobilisation costs separate from the rate so short and long hire durations can be compared on the same basis.
- 03
State hours, shifts and programme
State the proposed dates, shift length and expected usage. Identify weekends, restricted working windows and likely interruptions. Request the included hours and minimum charging period in each response rather than converting rates without checking their basis.
- 04
Request exclusions in writing
Use an inclusions table covering attachments, operators, fuel, servicing and return condition. Mark unanswered items as awaiting confirmation. Keep the accepted quote version with any later change so an informal clarification does not disappear from the decision record.
Evidence to retain
Keep the issued scope, supplier response, machine details, agreed substitutions, pricing schedule and approval record together. A short written trail protects both the project team and supplier when plans change.