P-01 / PROCUREMENT CONTROL

Build a comparable machinery RFQ

Turn a project need into an enquiry that produces comparable offers rather than a collection of incompatible day rates.

Why this control matters

Machinery hire decisions become difficult to compare when requirements remain implied. This protocol creates a compact evidence trail: what the project needs, what the supplier has offered, what remains to be confirmed and who owns the next decision.

Control sequence

  1. 01

    Define output and working envelope

    Describe the quantity, material, required result and working position. Attach a plan with dimensions. Ask suppliers to state the proposed machine class and how it meets those inputs; keep productivity estimates identified as assumptions until the site has been assessed.

  2. 02

    Separate base hire from mobilisation

    Ask for delivery and collection as separate line items, including origin, waiting and loading assumptions. Keep fixed mobilisation costs separate from the rate so short and long hire durations can be compared on the same basis.

  3. 03

    State hours, shifts and programme

    State the proposed dates, shift length and expected usage. Identify weekends, restricted working windows and likely interruptions. Request the included hours and minimum charging period in each response rather than converting rates without checking their basis.

  4. 04

    Request exclusions in writing

    Use an inclusions table covering attachments, operators, fuel, servicing and return condition. Mark unanswered items as awaiting confirmation. Keep the accepted quote version with any later change so an informal clarification does not disappear from the decision record.

Evidence to retain

Keep the issued scope, supplier response, machine details, agreed substitutions, pricing schedule and approval record together. A short written trail protects both the project team and supplier when plans change.

Practical answers before you hire

When should I use “Build a comparable machinery RFQ”?

Use this control when preparing or reviewing the relevant part of your hire arrangement. Start with: define output and working envelope. Keep the supplier response and unresolved items with the booking.

What if the supplier changes the arrangement?

Record the change and have the responsible person reassess the affected scope, equipment and terms. Send the approved version to the people receiving the machinery.