P-03 / PROCUREMENT CONTROL

Read transport and mobilisation

Expose the freight, permits, escort, float and demobilisation assumptions that can reshape the final cost.

Why this control matters

Machinery hire decisions become difficult to compare when requirements remain implied. This protocol creates a compact evidence trail: what the project needs, what the supplier has offered, what remains to be confirmed and who owns the next decision.

Control sequence

  1. 01

    Identify mobilisation origin

    Ask where the machine will actually depart from and whether it needs a transfer before delivery. A business's headquarters may differ from the dispatch depot. Put the origin and destination on the quote comparison so freight assumptions remain visible.

  2. 02

    Check permits and escorts

    Give the transport provider the machine dimensions, weight and route information needed to assess the movement. Ask the provider to identify applicable route, permit or escort arrangements with the relevant authorities and include their responsibilities in the offer.

  3. 03

    Confirm loading responsibility

    Confirm who loads and unloads, which equipment is needed and where the receiving vehicle can stand. Reserve the unloading area in the programme and identify the site contact. Ask how waiting is charged if the area is unavailable.

  4. 04

    Price demobilisation separately

    Confirm the return destination, collection notice and pricing assumptions. A one-way delivery price does not establish the total transport cost. For projects that move between workfronts, request separate treatment of intermediate transfers and final collection.

Evidence to retain

Keep the issued scope, supplier response, machine details, agreed substitutions, pricing schedule and approval record together. A short written trail protects both the project team and supplier when plans change.

Practical answers before you hire

When should I use “Read transport and mobilisation”?

Use this control when preparing or reviewing the relevant part of your hire arrangement. Start with: identify mobilisation origin. Keep the supplier response and unresolved items with the booking.

What if the supplier changes the arrangement?

Record the change and have the responsible person reassess the affected scope, equipment and terms. Send the approved version to the people receiving the machinery.